Client: Water Authority of Jordan
Location: Mudawwara/Jordan
Services Provided: Design & Supervision
on construction
Starting Date: 9/1990
Completion Date: 6/1993
Planning Data: -Sewers: 2770m
-Infiltration pond
80mx80m
-Pumping station
(No.2)10m3 /hr at
12m
Construction Cost: US $ 360,000


The purpose of this project which is located at the Jordan Saudi Arabia border at a distance of 350 km from Amman is to construct main sewers, house connections, sewage treatment facilities to improve health conditions and reduce mosquitoes.

Services:
- Preliminary engineering design.
- Final detailed design.
- Preparation of tender documents.
- Construction Supervision.

 